Advertisement

Opal Tower residents could wait months before repairs are finished

Hundreds are still homeless as the latest report finds Opal Tower beams 'burst' under pressure

Hundreds are still homeless as the latest report finds Opal Tower beams 'burst' under pressure Photo: AAP

The owners corporation behind the Opal Tower says it has “many questions” to be answered before it approves a plan by the builder for repairs on the damaged building – meaning residents could be homeless for months.

Icon, the builder of the 36-storey apartment complex evacuated on Christmas Eve after residents heard a loud cracking noise, told the ABC it expected remediation works on the tower to take another “four to six weeks”.

However the Opal Tower owners corporation – which has employed an independent engineer to asses the building – needs to give Icon the green light before any repairs can occur.

The owners corporation, headed by resident Shady Eskander, said it was committed to ensuring all decisions were made with “a proper process”, and called for a detailed management plan to be developed.

It means residents face a continued wait before they can return to their homes, which could potentially stretch well beyond the two-month mark.

The move came after the NSW State Government on Friday released its final report into the building, following a near two-month investigation.

The report found problems caused by changes made after the original Opal Tower design were exacerbated by “construction issues”, with “lower-strength concrete” and “under-designed” critical support beams bursting under extreme pressure.

Icon confirmed 259 units in the 392-unit apartment complex at Sydney’s Olympic Park are still empty, with hundreds of families still in temporary accommodation.

Many have vowed never to return.

In a statement, Icon told the ABC it “welcomed the Government’s findings” and believed the construction-related issues identified in the report had been “satisfactorily addressed”.

“Icon is performing remediation work in seven areas of the building: two areas on level 4, two areas on level 10 and three areas on level 16,” the company said.

“Remediation plans have been finalised and issued to the body corporate (owners corporation) for consent which Icon hopes will be provided without delay, as recommended by the report.”

“Once consent is given, Icon anticipates the works will take approximately four to six weeks to complete.

“Icon is ready to undertake these works immediately.”

Temporary structural supports inside the Opal Tower. Photo: AAP

The Opal Tower owners corporation said it had been actively seeking more information from all parties since the date of the incident.

“[We] have only received initial remediation plans eight weeks after the incident on Christmas Eve,” it said in a statement.

“All residents are eager to return home but [we have] many questions that have arisen and need to be addressed with Icon in order for approval to be provided.”

“As the NSW Government has also just released their findings, the owners corporation must digest all information provided, and would only issue approval to commence remediation after taking into consideration the independent opinions of all experts involved.”

In the meantime, experts have warned of an “Opal Tower” effect causing a “feeding frenzy of negativity” in the off-the-plan apartment market.

Large cracks appeared in the Opal Tower, prompting its evacuation. Photo: ABC

Some residents have openly questioned whether they will ever be able to sell their apartments, some of which were originally valued at $2.5 million.

Ecove, the developer behind the project, said it welcomed the report on the building’s faults. It described the process as “devastating”.

“It is extremely concerning to have it confirmed again in this final report that changes made after the original design and exacerbated by construction issues appears to lie at the core of the problem,” Ecove said in a statement.

“Ecove supports any initiative to ensure the integrity of the design and construction process, and return confidence to the community and to the building and construction industry.”

-ABC

Stay informed, daily
A FREE subscription to The New Daily arrives every morning and evening.
The New Daily is a trusted source of national news and information and is provided free for all Australians. Read our editorial charter
Copyright © 2024 The New Daily.
All rights reserved.