WestConnex $700m blowout revealed in leaked letters

WestConnex contractors have demanded another $700 million to finish the second stage of the controversial project, leaked letters show.
The NSW opposition released the confidential letters on Thursday to reveal the new M5 could also be one year behind schedule.
The letters, seen by The New Daily, reveal CPB Dragados Samsung Joint Venture demanded an extra $625 million in âcontractor delay costsâ and another $79.7 million in âchange costsâ in May 2017.
The completion date was also put at January 2021, a year after the governmentâs claim.
WestConnex Minister Stuart Ayres said the M5 was still on track to open in early 2020, and had not blown out its $4.335 billion budget.
âWestConnex continues to be on time and on budget,â Mr Ayres said in a statement to The New Daily on Thursday.
âContract claims and variations are part of the delivery of any large-scale infrastructure project.â
Premier Gladys Berejiklian denied the M5 budget had blown out in Question Time on Thursday, but conceded every project had âchallengesâ.
Opposition leader Luke Foley said the dispute revealed the âobsessive secrecy of the governmentâ and its âwaste and incompetenceâ.
âScandalously, theyâve kept this hidden,â he said.
The dispute goes back to at least August 2016, when the first confidential letter leaked by Labor was dated.
The leaked documents come as the government battles Spanish subcontractor Acciona in court over a $1.2 billion dispute for the delayed light-rail project.
On Tuesday, the third stage of WestConnex suffered a blow when the Supreme Court knocked back the governmentâs bid to compulsorily acquire commercial land at Rozelle in Sydneyâs inner west.
âHot on the heels of the Sydney light-rail scandal, yet another Berejiklian government infrastructure project is plagued by cost blowouts and delays in delivery,â Mr Foley said.
-With AAP